Freezer farm construction area, parking lot, administrative wing, Pathology Research and Special Coagulation
Time Affected:
Monday, April 27, 2026 to Friday, May 1, 2026
Impact Details
This work is part of the construction of a new freezer farm room on the first floor at 3375 Hillview Avenue that began on February 9
A freezer farm is a large facility filled with ultra‑low‑temperature freezers used to securely store biological samples and temperature‑sensitive pharmaceuticals
Upcoming work includes installing a new condenser line for the heating, ventilation, and air conditioning (HVAC) unit and updating electrical connections to safely support freezer operations
Work schedule:
Monday, April 27 and Tuesday, April 28: Condenser line installation, electrical relocation, and tape and paint
Wednesday, April 29: Condenser line installation, electrical relocation, and flooring install
Thursday, April 30: Flooring install and patch and paint
Friday, May 1: Clean area and prep for freezer install
Anticipated Impacts and Mitigation:
Building occupants may experience some noise on second floor
Dust containment will be installed at the entrance to Room 2704 and the breakroom